Project Cost Management
Tangible cost: measurable
Intangible cost: unmeasurable
Direct cost: directly involved in the project
Indirect cost: cost of shared resource
Sunk cost: spent in the past
Fixed cost:
Variable costs:
Commited cost:
Earned value analysis example
I am running a carpentry workshop and have recently received an order for manufacturing
100 doors for an apartment complex in 20 days for a price of $30,000. My estimated cost for
making the doors is $24,000. After 6 days my workers have completed 32 doors. I figured
that I have spent $15,040 on materials and labour.
Planned value (PV) = (42000/100)*30 = 12600
Earned value (EV) = (42000/100)*32 = 13440
Actual cost (AC) =15040
Schedule Variance (SV) = EV - PV = 840
Cost Variance (CV) = EV - AC = -1600
Schedule performance index (SPI) = EV/PV = 13440/12600 = 1.067
Cost performance index (CPI) = EV/AC = 13440/15040 = 0.89
Estimate to complete (ETC) = 68 * (15,040 / 32) = 31,960
Expected at completion (EAC) = AC + ETC = 47,000
Variance at completion (VAC) = BAC - EAC = 42,000 - 47,000 = -5,000
Budget at completion (BAC) = 42,000
Percentage of work completed (PC) = EV/BAC = 13440/42000 = 32%
Percentage of money spent (PS) = AC/BAC = 15040/42000 = 36%
Comments
Post a Comment